Alteva/Momentum Telecom
Client
Kaiserman Company 400 Market St.
Project Type
Building Renovation
About The Project
Details: Fit-out of Alteva/Momentum Telecom’s operations and marketing center. It was a full gut renovation of an existing office space, including removal of years of abandoned telecom, electrical, mechanical equipment, sprinkler lines and equipment.
This project involved numerous time and logistical challenges. A big hurdle was assuring we would not disturb the two tenants below them 94.1 WYSP Sports Radio and 98.1 Oldies Radio stations. The excessively noisy demo, core drilling and metal framing for walls had to be closely coordinated to assure they were on “pre-recorded loop tape” or on “remote location broadcast” modes. We were successful in integrating our work with their operations, and no disturbances to on-air shows occurred.
We also had to coordinate construction related deliveries, contractors and inspectors so they did not interfere with the other tenants, guests or the building management in any way.
The timeline allowed for approximately 60 days from start of demo to occupancy permit. Given the rectilinear construction, the mechanics of “building” the space out was not nearly as challenging as it was to assure all long lead time custom items, such as the Allure Glass Wall Systems, custom LED fluorescent lighting and acoustic ceiling systems that needed to be ordered, measured, manufactured and installed in a timely manner.
All work was completed on time and budget, expending zero dollars from the contingency fund.